UPS replacement and modernization planning in Toronto

Every UPS reaches the year its manufacturer stops guaranteeing parts. A replacement plan puts that year on the calendar for each unit, next to its condition from the last visit, and turns the list into a budget by year. The output is an asset list, a recommendation per unit and a sequence that never leaves a load unprotected.

Request a quoteCall 1 (438) 800-0382

Key facts

  • Two separate dates: when a model stops selling, and when full parts and labour support ends
  • Eaton's best-efforts phase: limited parts, replacement recommended[1]
  • Wear parts inside the frame: batteries every 3 to 5 years (lead acid), capacitors around 7 years (Eaton) [2] [3]
  • Lithium-ion batteries: 10 to 15 years (Eaton)[2]

Sales status is not service status

A discontinued model can keep full support for years, and a model still on sale can already have its best-efforts year set. Eaton’s catalogue lists the 9390 as discontinued, with the 93PM named as comparable [4]. Its service table keeps the 9390 in full support until best efforts begin in 2027 at 208 V and 2028 at 480 V [5]. A plan built on sales status alone replaces equipment too early or too late.

End-of-support calendar

Year Model What changes
2026 APC Symmetra PX, SY150K250D frame Schneider’s end-of-service date, Apr 27, 2026 [6]
2026 Mitsubishi 9900A Best Effort Support ends 12/2026, projected [7]
2027 Eaton 9390 208V Best efforts begin [5]
2027 Mitsubishi 9800A-E Best Effort Support ends 03/2027 [8]
2027 Mitsubishi 9700 Sustained Support ends 09/2027 [9]
2028 Eaton 9390 480V Best efforts begin [5]
2028 Eaton BladeUPS Best efforts begin [10]
2030 MGE Galaxy 5000, G5TUPS80 Schneider end of service, Dec 31, 2030 [11]
2031 MGE Galaxy 7000, G7TUPS500 Schneider end of service, Dec 31, 2031 [12]
2032 Eaton 93PM, first generation Best efforts begin [13]
2033 Eaton 9355 and Power Xpert 9395 Best efforts begin [14] [15]
2034 Eaton 9155 Best efforts begin [16]

Vertiv, Toshiba, Tripp Lite and Delta dates come from each manufacturer’s own pages for the exact model. Where a manufacturer publishes none, the plan says so and leans on parts availability and condition.

How a plan is built

  1. Asset list: make, model, serial, install date, battery date and measured load for every UPS.
  2. Manufacturer status: sales status and service phase, with dates, from the manufacturer’s documents.
  3. Condition: battery resistance trend, wear parts due, alarm history, from the last maintenance visit.
  4. Options per unit: keep and maintain; a life-extension programme where the manufacturer offers one; like-for-like replacement; or a modern frame.
  5. Budget by year, with the changeovers sequenced so each load moves to bypass or a temporary UPS once.

Modernization options

Option What it changes
Lithium-ion batteries, in frames built for them 10 to 15 years of battery life instead of 3 to 5 (Eaton) [2]
Modular frame Capacity added by module, and N+1 inside one frame
High-efficiency mode Up to 99% in Eaton’s ESS mode on the 93PM 480V, 97% in double conversion [17]
Right-sizing A frame matched to the measured load instead of the original nameplate

Common questions

How long does a UPS last?

The frame lasts until its manufacturer moves it to best-efforts support, which for the Eaton 9155 begins in 2034 [16]. Inside that life, lead-acid batteries are replaced every 3 to 5 years [2] and Eaton schedules capacitors around 7 years [3].

When should a UPS be replaced?

Before its best-efforts or end-of-service year, when the load has outgrown it, or when a repair costs a large share of a new unit. A plan sets that year in advance instead of after a failure.

Is my UPS discontinued?

Check two things: the manufacturer's product page (sales status) and its end-of-service-life table (service phase). Send the model and serial through the request form and we read both.

Can an old UPS be upgraded instead of replaced?

Sometimes: a battery type the manufacturer approves for the frame, a life-extension programme, or added modules on modular systems. Where none of those exist, replacement before the end-of-service year is the safer plan.

Sources

  1. Eaton, Eaton UPS End of Service Life (EOSL) Master Table, PL161010EN rev 05/29/2026, p1 legend (pdf.js row text)
  2. Eaton, Lithium-ion UPS FAQ, FAQ
  3. Eaton, Straight talk about capacitors in your UPS (WP153009EN), capacitor service life section
  4. Eaton, Eaton 9390 UPS (discontinued), product page banner
  5. Eaton, Eaton UPS End of Service Life (EOSL) Master Table, PL161010EN rev 05/29/2026, p4, rows 9390-20-40 208V and 480V (pdf.js row text)
  6. Schneider Electric Canada, Symmetra PX 150 kW scalable to 250 kW (SY150K250D), product page notices
  7. Mitsubishi Electric Power Products, UPS Product Lifecycle and Support, Best Effort Support table
  8. Mitsubishi Electric Power Products, UPS Product Lifecycle and Support, Best Effort Support table
  9. Mitsubishi Electric Power Products, UPS Product Lifecycle and Support, Sustained Support table
  10. Eaton, Eaton UPS End of Service Life (EOSL) Master Table, PL161010EN rev 05/29/2026, p4, row BLADEUPS-12 (pdf.js row text)
  11. Schneider Electric Canada, MGE Galaxy 5000 80 kVA (G5TUPS80), product page notices
  12. Schneider Electric Canada, MGE Galaxy 7000 500 kVA (G7TUPS500), product page notices
  13. Eaton, Eaton UPS End of Service Life (EOSL) Master Table, PL161010EN rev 05/29/2026, p4, rows 93PM-20-50 Gen 1 and 93PM 208V-20-60 (pdf.js row text)
  14. Eaton, Eaton UPS End of Service Life (EOSL) Master Table, PL161010EN rev 05/29/2026, p4, row 9355-10-15: Active - Full Support 2009, Mature - Best Efforts 2033 (pdf.js row text)
  15. Eaton, Eaton UPS End of Service Life (EOSL) Master Table, PL161010EN rev 05/29/2026, p4, row 9395-275-275-CA (pdf.js row text)
  16. Eaton, Eaton UPS End of Service Life (EOSL) Master Table, PL161010EN rev 05/29/2026, p2, row 9155-8-10 (pdf.js row text)
  17. Eaton, Eaton 93PM 480V UPS, overview