Before a UPS maintenance window

A UPS maintenance window goes well when the site has settled four things in advance: the written method, whether redundancy will hold while a unit is out, whether the generator can take the load if the utility drops, and who has to be in the room. Most of the risk in a window is in the minutes the load spends on bypass, when it runs on mains power with no battery behind it [1].

Request a quoteCall 1 (438) 800-0382

Key facts

  • On bypass: mains power to the load, only while the input stays within limits[1]
  • Concurrent maintainability: Tier III design lets planned work proceed with the IT load running[2]
  • Modular frames: at least one power module stays in while another is swapped (XPC M90)[3]
  • Visit frequency: at least once a year (Eaton)[4]
UPS power pathsUtility power feeds the rectifier, the DC bus and battery string, then the inverter and the load. A static bypass and a maintenance bypass route around the UPS.Maintenance bypassStatic bypassUtilityRectifierInverterLoadDC busBattery stringNormal: rectifier and inverterOn battery: battery string and inverterStatic bypass: utility to loadMaintenance bypass: UPS isolated
During the window the load may run on maintenance bypass: mains power with no battery behind it.

The method of procedure

The method of procedure (MOP) is the script for the window. Agree it in writing before the day:

Item What it states
Starting state Which sources feed the load, which breakers are closed, what the UPS display should read
Redundancy during the work What still protects the load while each unit or module is out
Steps Every switching operation, in order, with the expected indication after each
Hold points Where work stops until the site contact confirms the state
Rollback How to return to the starting state from any step
Stop conditions An unexpected alarm, redundancy lower than planned, or labels that do not match the diagram
Names Who directs the switching, who verifies, who approves

If the diagram, the labels and the actual breaker positions disagree, the window stops until they agree.

Check the redundancy is still there

A frame installed as N+1 becomes N the day the load grows into the spare module, and nothing alarms. Before the window, compare the measured load on each phase with the capacity left after removing the largest module or unit. If the answer is less than the load, the work needs the maintenance bypass or a temporary unit instead, and the MOP has to say so. The redundancy guide covers the check.

Check the generator

While the load is on bypass, a utility drop reaches it directly. Confirm the generator’s last test date and the transfer switch position before the window, and keep the window short. Count usable fuel, not tank size: fuel below the pickup, a delivery that depends on one supplier, or a test that burned a day’s worth all shorten the real runtime.

The week before

  • Battery readings: pull the last report. A block that has drifted more than 50% from its baseline needs a decision first [5].
  • Event log: note any open alarms, so the technician does not chase an old one.
  • Access: escort, loading dock, permits and lockout rules booked.
  • Monitoring: tell the NOC which alarms the window will raise, and for how long.
  • Stakeholders: IT and facilities sign off on the window and the rollback.
  • Parts: fans, capacitors or batteries due on the last report ordered, so they arrive for the same window.

On the day

Run the site’s daily checks first: air intakes and exhaust clear [6], and the normal-operation indicator on. A red alarm indicator before the window starts is a reason to stop and call service [7]. Then follow the MOP, hold point by hold point.

Standards cited

  • Uptime Institute Tier Classification System (as published)
  • Eaton and Vertiv user manuals

Common questions

What is a method of procedure for UPS maintenance?

The written, step-by-step plan for the window: the starting state, every switching step with its expected indication, hold points, rollback and stop conditions, and who directs and verifies each step.

Does UPS maintenance need a shutdown?

Usually not. On a concurrently maintainable design, planned work proceeds with the IT load running [2]. On a single UPS, the load runs on maintenance bypass for part of the window, unprotected by the battery.

How long does the load stay on bypass?

As short a time as the work allows. The MOP states the expected time, and the window is planned around the generator being available.

What should we send the technician before the window?

The last report, the event log, the single-line diagram, the UPS make, model and serial number, and the site's access and safety rules.